Planner18 Planner18 is offline Slack on Critical Path?? Windows 8 Slack on Critical Path?? Office 2010 32bit
Novice
 
Join Date: Oct 2014
Posts: 14
Planner18 will become famous soon enough
Default

To see the true critical path, in project go to file / options / advanced, scroll to the bottom and uncheck ‘Calculate multiple critical paths’



All tasks must be linked, set to auto-schedule and have no links to summary activities/tasks.

Hope that helps
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
MS Project 2013 Critical Path Chris Waller Project 1 03-06-2019 01:40 PM
Critical path bijukn1 Project 2 11-04-2016 10:31 AM
Critical Path Length ketanco Project 5 03-15-2013 01:12 PM
critical path starting in future ketanco Project 5 07-27-2012 02:50 PM
Slack on Critical Path?? Critical Path w/ 2 Calendars AndreT Project 6 07-27-2011 11:22 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:04 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft