Old 09-24-2018, 12:40 AM
Patrick Geers Patrick Geers is offline Tasks cannot be linked Windows 7 64bit Tasks cannot be linked Office 2016
Novice
Tasks cannot be linked
 
Join Date: Sep 2018
Location: Eindhoven
Posts: 9
Patrick Geers is on a distinguished road
Default Tasks cannot be linked

I have several tasks within a WBS.
These tasks have no linked tasks (no predecessors and no successors).
The WBS however is linked to other WBS's (1 predecessor and 1 successor).




I want to link the tasks within the WBS but get the message:
"These tasks can't be linked because they're already linked through another task chain"


Again these task do not have any successors nor predecessors, their WBS does.


I expect to be able to link these tasks within the WBS.
Reply With Quote
  #2  
Old 03-06-2019, 01:33 PM
Guloluseus Guloluseus is offline Tasks cannot be linked Windows 7 64bit Tasks cannot be linked Office 2010 32bit
Competent Performer
 
Join Date: Mar 2013
Posts: 168
Guloluseus is on a distinguished road
Default

Take out the WBS links- they are bad practice, and make problems like this a lot more likely. It should always be tasks linked, a WBS is a cover all for other items, and as such has no actual presence.
There is no reason you cant have a milestone at the end of a WBS as a task and use this, but the actual WBS xauses more problems than anything else.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Outlook 365 My Tasks: Tasks vs. TodoList--Sort? markg2 Outlook 0 04-17-2016 03:21 AM
Tasks cannot be linked Excel linked dates and Tasks not respecting Successor Links davetaff Project 2 12-31-2015 02:51 PM
updating not completed tasks or 0% tasks ketanco Project 3 08-24-2012 05:59 AM
Tasks cannot be linked Doing a linked paste within a linked spreadsheet tkondaks Word 1 08-17-2012 12:23 AM
Export Excel tasks into Outlook Tasks (2007 Version on both) crazedmom Excel 0 12-29-2011 07:55 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:02 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft