The simple explanation is that an item is shown as critical if changing the duration would affect the completion date.
If you had a programme with 2 tasks, a and b, that occur concurrently. where a took 5 days and b took 3 days, a would show as critical, as any change to the duration would affect the completion date. If task b took 1 day or 4 days, it wouldnt matter to completion.

The critical path is not something you make, it comes out of the programme. Trying to manipulate a programme to manufacture a CP is never, ever a good idea- it means that tasks will have incorrect duration, incorrect links, or worse.

Think of it as Project telling you what items have to be done on time to avoid failing. as you change the programme the CP will change to reflect these changes.
Reply With Quote
 

Tags
critical, critical path, path



Similar Threads
Thread Thread Starter Forum Replies Last Post
Critical path bijukn1 Project 2 11-04-2016 10:31 AM
Question about tasks on critical path in MS Project schedule (with a twist) SomewhereinTX Project 7 01-06-2014 03:07 PM
Critical Path Length ketanco Project 5 03-15-2013 01:12 PM
critical path starting in future ketanco Project 5 07-27-2012 02:50 PM
MS Project 2013 Critical Path Critical Path w/ 2 Calendars AndreT Project 6 07-27-2011 11:22 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 10:42 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft