  #1  
Old 09-12-2018, 11:19 AM
ThinAirDesigns ThinAirDesigns is offline ALAP constraint behavior question Windows 10 ALAP constraint behavior question Office 2003
Novice
ALAP constraint behavior question
 
Join Date: Sep 2018
Posts: 5
ThinAirDesigns is on a distinguished road
Default ALAP constraint behavior question

Hi there. Moderate Projects user over the years with a scheduling need I've never encountered and I'm hoping I'm just ignorant of an easy solution. I'm currently using a very old 2002 version.



Attached is an image with three figures (all different screen shots from a simple 'project' created just to illustrate my issue). This sample project has 3 floating activities and a 'project completion' milestone which has an artificial hard completion date. The behavior of Activity #2 is what I'm attempting to control (I want the float gone).

All relationships are simple 'FS' with zero lag. Activities 1 and 3 are constrained 'ASAP' in all three figures.

In figure 1, Activity 2 is constrained 'ASAP' with the expected float reflecting the difference in duration between activities 1 and 2.

In figure 2, Activity 2 is constrained 'ALAP' which has taken the float out of Activity 2, but pushed Activity 3 down to the project end and the float is now reflected in the start of Activity 3.

Figure 3 is what I'm trying to achieve (without a hard constraint). I want the float gone between activities 2 and 3, but I can't have 3 pushed down to the end of the project. In other words, I want Activity 2 to be ALAP while Activity 3 is ASAP. This may sound like a directly conflicting requirement (and it may be as related to Projects' capabilities), but it's not conflicting if one thinks of activity 2 being ALAP relative to Activity 3 while Activity 3 is ASAP relative to the project as a whole.

Can this be done in Projects 2002? Any version of Projects? Any version of a CPM software?

Remember, it's the described principle I'm interested in -- it would be easy in this little snippet to just 'hard constrain' and get away with it, but I'm involved in a relatively large scheduling project and in such any hard constraints will really create issues as things are updated.

Thanks.
JB
Attached Images
File Type: jpg Untitled.jpg (94.4 KB, 18 views)

Last edited by ThinAirDesigns; 09-12-2018 at 05:03 PM.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
ALAP constraint behavior question Odd 2013 Behavior drnshaw Word 4 02-06-2015 04:41 PM
finish no later than constraint ketanco Project 1 10-25-2014 04:30 PM
ALAP constraint behavior question Start No Later Than constraint EC37 Project 3 05-13-2014 10:13 AM
ALAP constraint behavior question activities getting constraint dates vs starting as soon as possible ketanco Project 1 08-30-2012 05:27 AM
ALAP constraint behavior question Update Progress breaks with constraint benwimpory Project 1 03-14-2012 08:44 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:20 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft