![]() my last activity on the project was finishing lets say on November 1. When I put a finish no later than constraint to the last activity as something before november 1, such as October 31, it reduces the toatl float by 1 day and makes the total float of critical path as -1, which i understand but when i put a finish no later than constraint to that activity as november 2, nothing changes. should this not increase the total float of critical path? |
#2
|
|||
|
|||
![]()
I'm guessing you mean the total slack returns to zero? FNLT constraints (as long as they are not violated) will not add positive total slack. You are merely saying the task needs to finish by a certain date - but it can finish earlier. If you wish to add total slack - set a must finish on.
|
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
flag to indicate finish date does not equal baseline finish date | TCB | Project | 3 | 08-06-2014 02:49 PM |
![]() |
EC37 | Project | 3 | 05-13-2014 10:13 AM |
![]() |
SomewhereinTX | Project | 3 | 12-20-2013 10:25 AM |
![]() |
ketanco | Project | 1 | 08-30-2012 05:27 AM |
![]() |
benwimpory | Project | 1 | 03-14-2012 08:44 AM |