#2
|
|||
|
|||
|
So to answer my own question for the purposes of thread quality, turns out what I was looking for was a "zero free float" constraint (ZFF) and it's not available in MS Projects.
Did find a work-around that for my purposes serves about 98% of my needs. http://www.boyleprojectconsulting.co...osoft-project/ |
|
|