Hello,
- we are manufacturing desks in batches. - every batch has different number of desks - we schedule our work per batch and not per desk. for example: Task1: Batch 11, 34 desks is it possible to calculate in ms project the work needed for the task (34 desks) if i know the work needed for the production of one desk? thank you in advance |