#4
|
|||
|
|||
![]()
Natively, Project wont do this, but there is a work around.
1) set date to dd/mm/yy in preferences (as you have done) 2) Under the "Project) tab,Create a custom field and call it start date, finish date, or whatever dates you are trying to show. 3) in the custom field, click on "formula", then field -> date -> Start/finish or whichever. 4) Format bars (under "Format" tab) and choose the field you created. this will then show date as dd/mm/yy. hope that helps |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Copying diagram from excel to power point or word changes name of series in the diagram | DrNic | Excel | 0 | 02-18-2016 09:08 AM |
How to make a task adjust its end date depending on another task? (Newbie) | ravl13 | Project | 3 | 07-27-2014 06:10 PM |
Letter date changes when merging with Excel - not the format, the actual date! | Smallweed | Mail Merge | 1 | 02-07-2014 06:00 PM |
Date showing 01/01/84 in Network Diagram - Project 2010 | JHBPJF | Project | 1 | 05-04-2012 07:52 AM |
Task with Start date but no Due date? | bplat | Outlook | 0 | 01-12-2012 08:10 AM |