#2
|
|||
|
|||
![]()
Tools > Customize Fields
Field type is Duration. Click the Rename button if you want to rename it. Choose the Formula radio button then click the Formula button The formula is: ProjDateDiff([Finish],[Finish1],"standard") The 3rd argument is the calendar. if you don't use the standard calendar, put your calendar name there instead. Then you will need to Insert the field in the table. |
|