If there is a question mark in the duration box for project summary, it means that a task somewhere has not been given a duration. have a look through, you should find it and be able to update it so that the estimated duration for the project becomes confirmed.
Overall duration is dictated not just by the time between start and finish, but by calendars used. It will give the duration in terms of the protect calendar, so if you have another calendar for specific tasks this can make a difference.
Rounded days (as in your 26.33) are often a result of using edays- if you are using these in the programme, or have 24 hour working calendars (same thing effectively) this may be the cause.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
MS Project 2013 - Problem with wasted screen space in print view. scw1984 Project 1 03-26-2016 06:47 PM
MS Project - Start/end and duration. 4shome Project 1 01-15-2015 06:31 PM
MS project 2013 problem with duration How to add A fixed cost per day for the duration of the project? vdLRSA Project 3 08-11-2014 02:26 PM
Project Duration for Part Time Resources Kingrollo Project 5 11-20-2012 06:44 AM
Project baseline duration Alka Project 1 11-20-2012 05:09 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:38 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft