Hey guys.
Have left everything basically on default and I am having duration value problems.
So I have my task, and I have put the start date at 29/10/17, and the end date is 23/11/17. But for some reason the duration is showing up with "21days?" - aware that ? means estimated but that is far off. What it should be is 20 days.
Another example, in few places where the duration is 1 day - the start & fish date are not the same (add one day)
in the total duration of the project show number of days ...something like this 26.33 insead of 26
Any help is great though.
Thanks!