![]() Hi, I have been struggling to answer this for a while, be grateful for some help. Basically I have a plan with tasks and want to be able to manually key in the amount of time that a resource works on a task so that I can produce a burn-up graph showing whether the project is delivering against effort(work) as well as deadline. For example. Task A is planned to take 5 days work over 10 days duration but it completes in 8 days using 6 days work. Any suggestions as to the best way to achieve this would be welcome? Thanks Jon |