![]() |
|
|
|
#1
|
|||
|
|||
|
1. For "Duration" must be: 26751/3600=7.43 day and with formula roundup. result 7.43 to 8 day.
2. For "Finish" must be: start(31.05.2017)+8day=08.06.2017 (saturday workday) |
|
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
showing months in another duration column
|
ketanco | Project | 8 | 01-20-2015 07:27 AM |
Inconsistent Duration column for the same date ranges
|
ravl13 | Project | 3 | 07-28-2014 05:16 PM |
| start and finish dates exceeding duration | joday48 | Project | 0 | 06-27-2012 04:55 AM |
| remaining duration vs finish date | ketanco | Project | 3 | 02-17-2012 02:24 PM |
duration vs actual start and finish dates
|
ketanco | Project | 1 | 12-14-2011 09:06 AM |