Newby here
![]() |
#2
|
|||
|
|||
![]()
If its showing 8-12, then that will be the only working times available. You can check this by clicking the "work weeks" tab just below where your screenshot ends. Then click "details" on the right hand side. If you then click on a day in the pop up menu, it will tell you what the working times are for that calendar. NOTE that this is set as "standard" unless you decide to change it.
It appears that somehow the afternoon shift has been deleted from the standard calendar. If you want to reset it as default, click in the day you want, then click "Use project default tomes", which will reset the selected day or days back to the normal 2 shifts. Its also possible that if you have resources allocated, these could have their own calendars, but unlikley if you havent entered anything. |
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Change computer's time, and all appointment times in Outlook's calendar change | TimTDP | Outlook | 0 | 03-14-2017 06:56 AM |
![]() |
stardog | Word | 1 | 06-03-2016 03:41 PM |
MS Project -How to delete Change Working Time - For Calender | erikmar | Project | 11 | 09-05-2014 03:44 AM |
![]() |
Gmonty | Project | 3 | 08-05-2014 02:53 PM |
Set text in edit control on inspector window indicating time Outlook 2007 | saniltalathi | Outlook | 0 | 02-20-2009 08:43 AM |