JulieS JulieS is offline Task order - dependencys Windows 10 Task order - dependencys Office 2016
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

My guess is that there is a mis-match between your calendar and your definition of hours per day in Project. Turn on the display of time in File > Options, General. My guess is that you have dropped the definition of "hours per day" to below 8. However, the calendar still allows more than those hours for working time.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Insert SubProject after Task x? (Linking ConsolidateProjects to Task) surumadurum Project 1 04-05-2016 06:09 AM
How to make a task adjust its end date depending on another task? (Newbie) ravl13 Project 3 07-27-2014 06:10 PM
Task order - dependencys Copy and Paste of a Task...Including all of the Task's 'children'...to a new task KRTSTARRYNIGHT Project 1 07-01-2014 06:54 AM
Task order - dependencys Mid-Task resource scheduled 0 hours increasing task duration needlessly DarlaWeber Project 1 01-31-2014 02:30 PM
how to make the task starts next day if no time enough today(task can not be split) duraid Project 1 10-25-2010 08:31 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:00 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft