#1
|
|||
|
|||
|
So when I'm looking at the task information window, and I'm looking at the dependencies, I'm most concerned with which task is the long pole. Some of my tasks have 100+ dependencies. Is there a way to have their end date appear in the predecessors tab? Like the image below?
|
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
Predecessor not considered?
|
Puddlerunna | Project | 9 | 09-10-2014 08:13 AM |
| using a predecessor twice | ketanco | Project | 2 | 03-07-2014 04:52 PM |
Predecessor name displayed in a text field
|
Leah | Project | 7 | 02-07-2014 03:26 PM |
| Linking predecessor twice | ketanco | Project | 1 | 04-06-2012 08:49 AM |
New to project - Predecessor Question
|
geissap | Project | 1 | 01-20-2011 10:00 AM |