#1
|
|||
|
|||
|
I used to schedule on Primavera 8.3.3, and I could simply enter start, finish and the task would populate on those days. I am new to Project and am trying to put together a simple schedule. Is there any way to make it measure by full days and not fractions?
In the picture below, I would rather it said 3 days. We are working 4/10's 8-6 |
|
#2
|
|||
|
|||
|
You need to set your options up correctly. If a day is 10 hours, both your calendar and the "hours per day" setting need to be correct.
|
|