#1
|
|||
|
|||
|
I'm guessing your question is why is the bar on task 9 not 8 days? The bar is drawn to Free Slack - not Total Slack. If you want the bar to match the total slack - change the bar definition. |
|
| Thread Tools | |
| Display Modes | |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
Project Summary Task Duration incorrect
|
BarryB | Project | 3 | 08-31-2016 02:43 AM |
Roll Up Summary Name does not appear on gantt chart
|
dnantia | Project | 3 | 02-13-2016 12:30 PM |
Negative total float
|
loukas | Project | 2 | 11-29-2015 10:38 AM |
| Rollup Summary Tasks to Project Summary Task | shep555 | Project | 1 | 05-24-2014 12:28 PM |
| 'Group By' Summary Duration Incorrect | hmcleay | Project | 3 | 03-01-2013 05:40 AM |