Resource Reports not showing Sub project Resource group hours
 
Join Date: Feb 2017
Posts: 2
RichB is on a distinguished road
Default Resource Reports not showing Sub project Resource group hours


I need to create a report that shows “work” or “remaining work” across time at a resource group level. The visual report works correctly on each individual project (as per image 1). I have created a master template & assigned several sub projects to this.

However when trying to view the cumulative hours across a resource group across sub projects in a master, I am unable to create the report when filtered on the relevant level. (image 3)
The number of hours that appears in the field “Remaining Work” is correct at a Resource Group level – ie – it adds the hours per resource within the relevant resource group. Plus when broken down a resource level, the hrs are shown (image 2)

However when I filter this over time, at a group level no hours are calculated?



I have tried using a Resource Pool & by just using a master Document & copying the resource names each time, so the naming conventions are common, both show the correct figures, but when they are filtered at a task level in the sub project version – the data is blank?

Thank you for your help
Attached Images
File Type: jpg Image 1.JPG (83.2 KB, 16 views)
File Type: jpg Image 2.JPG (87.4 KB, 16 views)
File Type: jpg Image 3.JPG (101.3 KB, 16 views)
Reply With Quote
 

Tags
resource groups, sub projects



Similar Threads
Thread Thread Starter Forum Replies Last Post
Fixed Hours for Resource Planning ebilbrough Project 1 12-28-2016 11:47 AM
Resource Reports not showing Sub project Resource group hours Project 2013 - Issue with Resource Usage showing wrong dates michaelwex Project 1 02-11-2016 08:41 AM
Resource Reports not showing Sub project Resource group hours Seperate Cost per Resource Group and Taskname Emanol Espina Project 6 12-17-2015 02:59 PM
Resource Reports not showing Sub project Resource group hours Resource not getting enough hours allocated to them, therefore extending duration joday48 Project 1 08-01-2014 08:54 AM
Resource Reports not showing Sub project Resource group hours Gantt bar text labels - possible to put resource hours against the bars? mtbtomo Project 5 05-14-2014 01:18 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:01 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft