JulieS JulieS is offline Manage external task dependencies Windows 10 Manage external task dependencies Office 2016
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Just to chime in. Linked master projects, particularly with 100 subprojects, are very prone to corruption. Renaming a file or moving a file is a quick way to create hours of grief. Tony - stick with what you have and I'm glad you discovered that they should update as long as the files are not renamed or moved.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Manage external task dependencies Copy and Paste of a Task...Including all of the Task's 'children'...to a new task KRTSTARRYNIGHT Project 1 07-01-2014 06:54 AM
single task with combine SS and FF dependencies Blobb Project 3 06-04-2014 12:24 PM
Cross Project Dependencies OTPM Project 6 01-18-2014 07:52 AM
Filter indirect dependencies SirPercival Project 1 07-04-2012 01:03 PM
Impossible task: sort email to external folder billzinn Outlook 1 07-26-2011 06:25 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:41 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft