Hello Tony, the thing you describe is what the purpose of a master plan is.
Instead of opening all plans, consolidate them into a master plan and do your work there.

Could be worth a try for you to explore this function. New plans can be added as sub plans into the master plan.

If you also have the need for a view of allocated resources shared between the plans this is a nice way to get there.

But on the other hand, if you have a way of working that works for you, roll with it!
If its not broken, dont fix it.

Cheers
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Manage external task dependencies Copy and Paste of a Task...Including all of the Task's 'children'...to a new task KRTSTARRYNIGHT Project 1 07-01-2014 06:54 AM
single task with combine SS and FF dependencies Blobb Project 3 06-04-2014 12:24 PM
Cross Project Dependencies OTPM Project 6 01-18-2014 07:52 AM
Filter indirect dependencies SirPercival Project 1 07-04-2012 01:03 PM
Impossible task: sort email to external folder billzinn Outlook 1 07-26-2011 06:25 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:39 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft