Finally I used the WBS field.
It works great, even after adding a new task.

New filter>


field name>WBS test>equals value> 1.1* etc...

Thanks anyway

Hillel
Reply With Quote
Reply

Tags
filtering, summary tasks



Similar Threads
Thread Thread Starter Forum Replies Last Post
Rollup Summary Tasks to Project Summary Task shep555 Project 1 05-24-2014 12:28 PM
filtering a single summary task. Task not rolling up after single task was baselined Hwlr Project 1 06-05-2013 03:43 PM
filtering a single summary task. Summary Report for Individual Task tmanzan Project 7 01-15-2013 12:45 PM
Task and Summary Durations JR_12 Project 0 10-15-2011 05:07 PM
filtering recurring task pascal Project 0 05-05-2010 08:07 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:08 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft