Thanks Julie for a swift and wise answer!
I did indeed not attach the resource pool to the subproject files. I thought the procedure was to create master file, then add subprojects and then pool the resources to the master file. As I understand it I have to use the resource pool on each subproject and then add them to the master file. Cheers! |
|