Microsoft Office Forums

Go Back   Microsoft Office Forums > >

 
 
Thread Tools Display Modes
Prev Previous Post   Next Post Next
  #1  
Old 01-23-2017, 08:15 AM
Campelliann Campelliann is offline Updating actual work and work on resource spread sheet Windows 8 Updating actual work and work on resource spread sheet Office 2016
Novice
Updating actual work and work on resource spread sheet
 
Join Date: Jan 2017
Posts: 6
Campelliann is on a distinguished road
Default Updating actual work and work on resource spread sheet

Hi,



I need to calculate the allocation of my employees within the near future, for this I update weekly the actual work for their activities. I would like project to divide the remaining work evenly in the weeks left.. but project insists in crazy divisions that I donīt understand.

Example: Pedro has a project of 100 hours, and has worked 10 hours this week (90 hours remaining now). If the project is to be delivered within 3 weeks I would like project to assign automatically 30 hours for week (30x3=90).
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Fixing Work, % of actual work and Final Date in a task (while assigning resources) Campelliann Project 1 01-09-2017 06:15 PM
Updating actual work and work on resource spread sheet How to Input Actual Overtime Work caveman Project 13 03-31-2015 05:24 PM
Updating actual work and work on resource spread sheet Where have all my 'actual work' entries gone? flanjamin Project 3 11-24-2014 03:41 PM
Change Resource Time vs. Duration when Updating Work column lylel Project 3 07-23-2012 06:09 PM
Actual work in the future joday48 Project 3 07-06-2012 06:00 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:09 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft