Microsoft Office Forums

Go Back   Microsoft Office Forums > >

 
 
Thread Tools Display Modes
Prev Previous Post   Next Post Next
  #2  
Old 12-28-2016, 11:47 AM
JulieS JulieS is offline Fixed Hours for Resource Planning Windows 7 64bit Fixed Hours for Resource Planning Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Project assumes your work estimates were correct. If a resource works fewer or more hours than they were scheduled, Project will assume the remaining work+actual work is equal to the original work.
Adjust remaining work as needed when doing the reporting.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Fixed Hours for Resource Planning Resource not getting enough hours allocated to them, therefore extending duration joday48 Project 1 08-01-2014 08:54 AM
Fixed Hours for Resource Planning Fixed Work Hours - newbie question EC37 Project 7 06-04-2014 06:19 AM
Fixed Hours for Resource Planning Gantt bar text labels - possible to put resource hours against the bars? mtbtomo Project 5 05-14-2014 01:18 PM
Fixed Hours for Resource Planning Mid-Task resource scheduled 0 hours increasing task duration needlessly DarlaWeber Project 1 01-31-2014 02:30 PM
Fixed Hours for Resource Planning Fixed duration, fixed units, fixed work, effort driven. How, why and when use it all Evgeny Project 3 01-03-2013 06:45 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:22 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft