Fixed Hours for Resource Planning
 
Join Date: Nov 2015
Location: Austin, TX
Posts: 19
ebilbrough is on a distinguished road
Default Fixed Hours for Resource Planning

We use an operations master schedule for resource planning purposes. It covers operation tasks for our fiscal year. Some of the same resources that are part of the operations master schedule are also resources on specific projects. The master schedule is used to allocate time for those periods where personnel aren't working a specific project.



In my operations schedule resources have hours allocated thru the remainder of the fiscal year. Each week as personnel submit timesheets and after they are approved the future hours that have been pre-assigned are readjusting based on the actuals they've reported on their timesheet.

Is there a way to fix these hours so that future hours don't change? The tasks in the master schedule are typically fixed duration. I've experimented with changing a couple to fixed work but that doesn't seem to fix the problem.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Fixed Hours for Resource Planning Resource not getting enough hours allocated to them, therefore extending duration joday48 Project 1 08-01-2014 08:54 AM
Fixed Hours for Resource Planning Fixed Work Hours - newbie question EC37 Project 7 06-04-2014 06:19 AM
Fixed Hours for Resource Planning Gantt bar text labels - possible to put resource hours against the bars? mtbtomo Project 5 05-14-2014 01:18 PM
Fixed Hours for Resource Planning Mid-Task resource scheduled 0 hours increasing task duration needlessly DarlaWeber Project 1 01-31-2014 02:30 PM
Fixed Hours for Resource Planning Fixed duration, fixed units, fixed work, effort driven. How, why and when use it all Evgeny Project 3 01-03-2013 06:45 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:39 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft