In a quick read it does appear that the former scheduler was approaching it in a fairly convoluted fashion. Insert the subprojects, and apply filters to show what you need.
If would also suggest only updating the subprojects and let those updates roll up to the master. The best option is to create a unlinked master for reporting. This can be automated using VBA to make the consolidation faster. |
|
![]() |
||||