Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 08-31-2016, 01:14 AM
BarryB BarryB is offline Project Summary Task Duration incorrect Windows 7 64bit Project Summary Task Duration incorrect Office 2013
Novice
Project Summary Task Duration incorrect
 
Join Date: Apr 2015
Posts: 19
BarryB is on a distinguished road
Default

HI Julie,

Thanks for the reply. Yes, that worked and I've learned something new.



Have a good day.
Reply With Quote
  #2  
Old 08-31-2016, 02:43 AM
JulieS JulieS is offline Project Summary Task Duration incorrect Windows 7 64bit Project Summary Task Duration incorrect Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Great. Glad you have it sorted and you're welcome for the information.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Project Summary Task Duration incorrect Showing how much work is required to complete a project according to summary task start/end times PDX-ADM-TRM01 Project 1 03-30-2015 04:05 PM
Rollup Summary Tasks to Project Summary Task shep555 Project 1 05-24-2014 12:28 PM
Project Summary Task Duration incorrect Mid-Task resource scheduled 0 hours increasing task duration needlessly DarlaWeber Project 1 01-31-2014 02:30 PM
'Group By' Summary Duration Incorrect hmcleay Project 3 03-01-2013 05:40 AM
Project Summary Task Duration incorrect summary task calculating from project start ketanco Project 1 01-02-2012 02:34 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:34 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft