Is there a reason why you are using the Task calendar versus editing the project calendar? Project Ribbon - change working time.
As a short term fix - apply the task calendar (if it will let you) to the Project summary task. The Project summary task is still using your definition of day (18 hours) but applying that against the working time in the Standard calendar. (8a - 5:00 pm, Monday through Friday) You would be better applying the changes (6 days per week, 18 hours per day) in the project calendar and removing the task calendars. |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
Showing how much work is required to complete a project according to summary task start/end times
|
PDX-ADM-TRM01 | Project | 1 | 03-30-2015 04:05 PM |
| Rollup Summary Tasks to Project Summary Task | shep555 | Project | 1 | 05-24-2014 12:28 PM |
Mid-Task resource scheduled 0 hours increasing task duration needlessly
|
DarlaWeber | Project | 1 | 01-31-2014 02:30 PM |
| 'Group By' Summary Duration Incorrect | hmcleay | Project | 3 | 03-01-2013 05:40 AM |
summary task calculating from project start
|
ketanco | Project | 1 | 01-02-2012 02:34 PM |