Old 08-16-2016, 03:44 AM
JulieS JulieS is offline Adding task costs Windows 7 64bit Adding task costs Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

When did you save the baseline? Before you added all tasks? Did you save a baseline only for selected tasks and not chose to roll the up? Have you tried saving a new baseline? Did you actually save the baseline or just type in the dates? I don't see a save date on the baseline.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Costs A B C D cajos Project 1 03-24-2016 06:26 AM
Adding task costs Materials/Work Costs Per task cool28uo Project 1 02-01-2015 03:59 PM
Adding task costs Copy and Paste of a Task...Including all of the Task's 'children'...to a new task KRTSTARRYNIGHT Project 1 07-01-2014 06:54 AM
Adding task costs Costs are not adding to the summary task in cost1 column ketanco Project 1 06-14-2012 03:23 PM
Adding task costs Non-recurring costs (NRE) Trigger Project 1 04-26-2012 03:41 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:08 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft