My first suggestion is to re-work the organization of your project. I would not use departments as summary tasks, but rather logical project and task break downs. If you create resources (even as basic as department names) you can then filter, group, or highlight tasks assigned to the departments.
Can you post a picture of the project as it is and I may be able to be more helpful. |
![]() |
|
![]() |
||||