#1
|
|||
|
|||
![]()
Just asking to see if someone might already have developed something to check and report where:
Duration contains ? Milestone has duration > 0 Incomplete Tasks with dates in the past Tasks without predecessors/successors Tasks with lags/leads on dependencies Relationships other then FS Hard constraints checks High Float check Negative float check High duration check I have custom filters but very manually intensive, looking to see if anyone has macros, VBA or reports that cover each or all of the above? |
Tags |
macor, planning quality, vba |
|
![]() |
||||