JulieS JulieS is offline Total Slack Calculation Incorrect in SubProjects vs MasterPlan Windows 7 64bit Total Slack Calculation Incorrect in SubProjects vs MasterPlan Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default


Are you opening subproject A outside of the master project? If so, it is not calculating the negative slack due to its relationship to project B.
Reply With Quote
Reply

Tags
masterplan, subprojects, total slack



Similar Threads
Thread Thread Starter Forum Replies Last Post
Total Slack Calculation Incorrect in SubProjects vs MasterPlan Very complicated calculation of total hours worked (PLEASE HELP) APreston Excel 1 05-08-2016 02:58 AM
Total Slack and Activity with SS Successor only ketanco Project 3 05-14-2014 01:59 PM
total slack of activities and schedule logic ketanco Project 1 08-04-2012 05:58 AM
Total Slack Calculation Incorrect in SubProjects vs MasterPlan total slack not changing when changing duration ketanco Project 1 02-11-2012 07:23 AM
Total Slack not updating damianb Project 0 06-25-2010 11:48 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:11 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft