#1
|
|||
|
|||
![]() Are you opening subproject A outside of the master project? If so, it is not calculating the negative slack due to its relationship to project B. |
![]() |
Tags |
masterplan, subprojects, total slack |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
APreston | Excel | 1 | 05-08-2016 02:58 AM |
Total Slack and Activity with SS Successor only | ketanco | Project | 3 | 05-14-2014 01:59 PM |
total slack of activities and schedule logic | ketanco | Project | 1 | 08-04-2012 05:58 AM |
![]() |
ketanco | Project | 1 | 02-11-2012 07:23 AM |
Total Slack not updating | damianb | Project | 0 | 06-25-2010 11:48 AM |