![]() |
|
#2
|
|||
|
|||
|
Do you have any tasks in the master project that are not part of the subproject? Normally negative total slack is from a missed deadline or constraint. Have you added constraints in the master project that are not in the subprojects?
|
| Tags |
| masterplan, subprojects, total slack |
| Thread Tools | |
| Display Modes | |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
Very complicated calculation of total hours worked (PLEASE HELP)
|
APreston | Excel | 1 | 05-08-2016 02:58 AM |
| Total Slack and Activity with SS Successor only | ketanco | Project | 3 | 05-14-2014 01:59 PM |
| total slack of activities and schedule logic | ketanco | Project | 1 | 08-04-2012 05:58 AM |
total slack not changing when changing duration
|
ketanco | Project | 1 | 02-11-2012 07:23 AM |
| Total Slack not updating | damianb | Project | 0 | 06-25-2010 11:48 AM |