Old 05-30-2016, 04:32 PM
JulieS JulieS is offline Total Slack Calculation Incorrect in SubProjects vs MasterPlan Windows 7 64bit Total Slack Calculation Incorrect in SubProjects vs MasterPlan Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Do you have any tasks in the master project that are not part of the subproject? Normally negative total slack is from a missed deadline or constraint. Have you added constraints in the master project that are not in the subprojects?
Reply With Quote
 

Tags
masterplan, subprojects, total slack

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Total Slack Calculation Incorrect in SubProjects vs MasterPlan Very complicated calculation of total hours worked (PLEASE HELP) APreston Excel 1 05-08-2016 02:58 AM
Total Slack and Activity with SS Successor only ketanco Project 3 05-14-2014 01:59 PM
total slack of activities and schedule logic ketanco Project 1 08-04-2012 05:58 AM
Total Slack Calculation Incorrect in SubProjects vs MasterPlan total slack not changing when changing duration ketanco Project 1 02-11-2012 07:23 AM
Total Slack not updating damianb Project 0 06-25-2010 11:48 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 12:27 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft