JulieS JulieS is offline Under utilization of resources Windows 7 64bit Under utilization of resources Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

How many Worker resources do you have? Resource Leveling in Project will never change assignment units. If you have 200% of workers and you have 200% assigned to Task B - Project will not drop assignment units to 100% during the time of Task A then increase it to 200% later on. You can manually contour resource assignments but Resource Leveling will not.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Under utilization of resources Resources - only allow users to select from resources pool grazi Project 1 04-04-2014 11:12 AM
Better way to views resources? ctobola Outlook 1 03-20-2014 08:01 AM
Multiple resources Tedzer Project 1 11-12-2013 08:02 AM
Under utilization of resources How to set task to be done by 4 resources each one after another? lukusm Project 1 01-16-2012 07:21 AM
Assigning resources. Sergey M Project 0 01-25-2006 09:33 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 11:31 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft