JulieS JulieS is offline conflicting tasks with exception days Windows 7 64bit conflicting tasks with exception days Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

If you want to allow only certain tasks to work over the weekend, you'll need to make a separate calendar with the weekend work allowed and assign that calendar to the specific tasks. Changing the project calendar affects all tasks.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Newbie question : detection of conflicting tasks Blitz Visio 1 03-03-2016 10:56 AM
conflicting tasks with exception days Changing color of a calendar exception c991257 Project 1 01-19-2016 05:40 PM
Exception days not accounted for in Gantt chart Splint Project 1 09-02-2014 05:58 AM
Database exception: login failed rkoziol7 Outlook 0 05-23-2011 01:07 AM
How to know if Meeting responses comes from serie or ocurrence/exception? frilian Outlook 0 07-13-2010 12:04 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:52 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft