Microsoft Office Forums

Go Back   Microsoft Office Forums > >

 
 
Thread Tools Display Modes
Prev Previous Post   Next Post Next
  #9  
Old 04-14-2016, 11:08 AM
rtuttle rtuttle is offline Start & Finish Date/Time Windows 7 64bit Start & Finish Date/Time Office 2013
Novice
Start & Finish Date/Time
 
Join Date: Mar 2016
Location: Greenville SC
Posts: 11
rtuttle is on a distinguished road
Default

I "cleared contents" in the cells and still had issues with start/finish time when I had "show project summary task" in the Zero line...

I highlighted the cells again and used "clear contents".... Summary dates still the same....Then used "delete tasks".. and the Summary was showing correct start/finish...

I have started a new project template and it is working.. Just need to get the resources entered
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Start & Finish Date/Time How to set a filter for tasks that will start & finish in two weeks? zislam14 Project 1 12-17-2015 03:58 PM
Start & Finish Date/Time Milestones with different start and finish dates ketanco Project 2 09-17-2014 05:21 PM
flag to indicate finish date does not equal baseline finish date TCB Project 3 08-06-2014 02:49 PM
Start & Finish Date/Time duration vs actual start and finish dates ketanco Project 1 12-14-2011 09:06 AM
MS Project able to import actual start and or actual finish date from Excel? mhacker Project 0 04-26-2010 11:29 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:58 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft