![]() |
|
#2
|
|||
|
|||
|
My guess is the Project start time was not updated when the calendar was changed to start at 8:30. What is the start time in the calendar? (Change working time). What is the default start time (File > Options, Schedule).
|
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
How to set a filter for tasks that will start & finish in two weeks?
|
zislam14 | Project | 1 | 12-17-2015 03:58 PM |
Milestones with different start and finish dates
|
ketanco | Project | 2 | 09-17-2014 05:21 PM |
| flag to indicate finish date does not equal baseline finish date | TCB | Project | 3 | 08-06-2014 02:49 PM |
duration vs actual start and finish dates
|
ketanco | Project | 1 | 12-14-2011 09:06 AM |
| MS Project able to import actual start and or actual finish date from Excel? | mhacker | Project | 0 | 04-26-2010 11:29 AM |