#3
|
|||
|
|||
|
Gangs for separate activites would be separate, so a paving op wouldnt be used drainage. reading my first post again, I think I missed out the important bit.
I get progs from other planners, who are a bit shy on resourcing. the best I am likely to get is "drainage gang", "surfacing gang" or similar. I need to replace this with a more detailed breakdown as one of our major clients requires it this way. I could go through the programme and filter by resource name, then paste in new resources, but it would be preferable if I could use a global setting that would do this for me. Sorry if I ama bit disjointed, too late really for me, probably look at this tomorrow and wonder what i was trying to say
|
| Thread Tools | |
| Display Modes | |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
resource assignment for multiple tasks
|
Yaroslav | Project | 1 | 01-25-2015 11:49 AM |
Resource assignment with resource calendars
|
joday48 | Project | 6 | 08-19-2014 05:49 AM |
| Resource Assignment Summary Line Not Adding Up Correctly | PeteS | Project | 2 | 07-18-2014 06:24 AM |
| Multiple resource Dependencies / Mapping | Sherry | Project | 3 | 04-03-2014 08:03 AM |
| Master Schedule and Multiple Resource Pools | calebhuzzah | Project | 1 | 06-23-2013 10:10 AM |