#1
|
|||
|
|||
![]()
It looks like somehow the bar style definition has gotten corrupt. Create a new bar style for summary tasks and it works fine.
By the way - you should not have resources assigned to summary tasks. |
#2
|
|||
|
|||
![]()
JulieS, thank you very much for prompt reply! Actually your reply made me "play around" a bit more with rolling up tasks and I discovered that if I click on a specific point on the main rollup summary bar, I can make it work! That I did not know really, that I actually have to click specifically on the black line bar which is visible during weekends..! Many thanks again, you opened my eyes! :-)
|
![]() |
|
![]() |
||||