![]() |
|
|
|
#1
|
|||
|
|||
|
It looks like somehow the bar style definition has gotten corrupt. Create a new bar style for summary tasks and it works fine.
By the way - you should not have resources assigned to summary tasks. |
|
#2
|
|||
|
|||
|
JulieS, thank you very much for prompt reply! Actually your reply made me "play around" a bit more with rolling up tasks and I discovered that if I click on a specific point on the main rollup summary bar, I can make it work! That I did not know really, that I actually have to click specifically on the black line bar which is visible during weekends..! Many thanks again, you opened my eyes! :-)
|
|
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
Gantt Chart
|
hdlarrain | Excel | 1 | 12-13-2015 03:13 AM |
Removing the Gantt chart from a view
|
raminraiszadeh | Project | 3 | 02-13-2015 01:24 PM |
| Excel Gantt Chart Help | kpk250 | Excel | 0 | 03-08-2013 08:46 AM |
| Bar in the Gantt chart with the duration | ms_user | Project | 3 | 01-11-2013 06:31 AM |
| move to first date on gantt chart | etsoft | Project | 3 | 12-23-2011 08:32 AM |