#2
|
|||
|
|||
![]()
I reinstalled it which fixed the 2007/2010 issue but the original issue with the tasks not respecting there Successor was sill there. I have found another way though. I have had to make the Sample delivery date a summary task. For some reason the Pre tasks then respect the link to the Post tasks. Looks a bit messier but it is a work around which works. If anyone knows what the original issue was please let me know. Thanks.
|
|
![]() |
||||