![]() |
|
#16
|
|||
|
|||
|
Hi,
You need to change the dependency to SS-3days; if you use fs-3 days you will get the start date as being 2 days earlier. because the day 1's will overlap. Hope this helps. Margaret |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
How to set a filter for tasks that will start & finish in two weeks?
|
zislam14 | Project | 1 | 12-17-2015 03:58 PM |
Finish to Start Tasks dates incorrect
|
Rowey | Project | 5 | 05-01-2015 07:22 AM |
% completion changes finish date?
|
Puddlerunna | Project | 9 | 11-25-2014 06:16 AM |
| flag to indicate finish date does not equal baseline finish date | TCB | Project | 3 | 08-06-2014 02:49 PM |
| remaining duration vs finish date | ketanco | Project | 3 | 02-17-2012 02:24 PM |