  #1  
Old 01-14-2016, 03:28 AM
Margaret Pate Margaret Pate is offline Tasks with different durations to all finish on specific date Windows 10 Tasks with different durations to all finish on specific date Office 2013
Novice
 
Join Date: Dec 2015
Posts: 12
Margaret Pate is on a distinguished road
Default

Any time
Reply With Quote
  #2  
Old 01-20-2016, 04:01 AM
dnantia dnantia is offline Tasks with different durations to all finish on specific date Windows 7 64bit Tasks with different durations to all finish on specific date Office 2010 64bit
Novice
Tasks with different durations to all finish on specific date
 
Join Date: Dec 2015
Posts: 16
dnantia is on a distinguished road
Default

Hello Margaret, sorry to bother you again but I would really like your help once more.
So I am trying to use what you have suggested and I am having a bit of problem with the starting dates that MS chooses automatically.

For example:
My project start date is 13 June.
Pick Up Point 1 I would like it to be at 1 July.
Pick Up Point 2 I would like it to be at 1 August.
Pick Up Point 3 I would like it to be at 1 Sept.

Phase 1 of server 1 lasts 3 days, so I have defined a 7fs-3d dependency.
Task 7 has a dependency with Pick Up Point 1 milestone.
So when I change the "Pick Up Point 1 milestone" date, I would expect that the starting date of phase 1 is automatically set to 3 days before the start date of task 7.
However this does not happen for some servers. Any idea why? I attach my mpp.
Thank you!
Nantia
Attached Files
File Type: zip nantia_semifinal_plan_v1.zip (508.9 KB, 10 views)
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Tasks with different durations to all finish on specific date How to set a filter for tasks that will start & finish in two weeks? zislam14 Project 1 12-17-2015 03:58 PM
Tasks with different durations to all finish on specific date Finish to Start Tasks dates incorrect Rowey Project 5 05-01-2015 07:22 AM
Tasks with different durations to all finish on specific date % completion changes finish date? Puddlerunna Project 9 11-25-2014 06:16 AM
flag to indicate finish date does not equal baseline finish date TCB Project 3 08-06-2014 02:49 PM
remaining duration vs finish date ketanco Project 3 02-17-2012 02:24 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:38 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft