Tasks with different durations to all finish on specific date
 
Join Date: Dec 2015
Posts: 16
dnantia is on a distinguished road
Default

Thanks a lot, I tried that but then when I move the milestone to the right for example, then indeed Subtask1b is properly "shifted" to the right, but Subtask1a remains in the same position... I would like Subtask1a to also move respectively to the right.



I attach a test.mpp. In this example, if the milestone moves, then subtasks "Pre-Checks" and "Backup" stay static although I would like them to also move. Probably my dependencies there are not ok.. I would appreciate some help, I have been struggling with this for so long!
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Tasks with different durations to all finish on specific date How to set a filter for tasks that will start & finish in two weeks? zislam14 Project 1 12-17-2015 03:58 PM
Tasks with different durations to all finish on specific date Finish to Start Tasks dates incorrect Rowey Project 5 05-01-2015 07:22 AM
Tasks with different durations to all finish on specific date % completion changes finish date? Puddlerunna Project 9 11-25-2014 06:16 AM
flag to indicate finish date does not equal baseline finish date TCB Project 3 08-06-2014 02:49 PM
remaining duration vs finish date ketanco Project 3 02-17-2012 02:24 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:59 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft