Hi Barry, % complete is a duration measure - not a work measure. Have you consumed 50% of the overall project duration? Try adding the Project Summary task (Gantt chart tools format ribbon). If you look at the project summary task - does the finish variance show 6 hours? Do you have tasks that are incomplete in the past? It appears so - you should not have task with zero % complete in the past that will certainly throw off the finish variance. |
|
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
MS Project 2013 - Overview report error
|
Imagios | Project | 15 | 02-05-2016 09:21 AM |
Project Reports Overview Milestone Filter
|
ebilbrough | Project | 2 | 12-17-2015 03:07 PM |
How to show planned% complete and actual% complete on the (Project Overview) dashboard report?
|
zislam14 | Project | 3 | 12-17-2015 03:03 PM |
| After open Project Overview Dashobard report, its blank | anurag9179 | Project | 3 | 01-15-2015 06:57 AM |
| Different % complete in Project Center & View a Project | mikaelbelchior | Project | 1 | 01-25-2006 12:56 AM |