#1
|
|||
|
|||
![]()
Hi,
(MS Project 2007 SP3) in normal cases you will use the resource graph to find over allocations and to correct them. I want to use the graph to show my resources (colleges) when they are planned for the different tasks. Please find picture 1. This shows you, what I have so far. Please find picture 2. This I want to have automatically from MS Project. ![]() Does anybody know how to do this? Thanks in advance! |
#2
|
|||
|
|||
![]()
Hi Mr. Stone,
Sorry, but I don't believe you can restructure the Resource Graph view to show the assignment data. You may have some luck exporting the timescaled data to Excel, and graphing there - but the resource graph in Project is not going to get you what you need as it only shows resource data, not specific assignment data. |
#3
|
|||
|
|||
![]()
First of all, thank you Julie.
It is better to have bad news than no news in this case. Meanwhile I upgraded from Microsoft Project 2007 to 2010. In MSP 2010 the view "team planner" is new and I think it is really useful for me (see picture 3). Thank you very much! ![]() |
#4
|
|||
|
|||
![]()
Great. I like the Team Planner too and I'm glad you were able to upgrade to 2010
|
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
codeghi | Project | 10 | 03-01-2014 08:13 AM |
![]() |
DarlaWeber | Project | 1 | 01-31-2014 02:30 PM |
![]() |
Evgeny | Project | 1 | 06-19-2013 06:55 AM |
![]() |
zapco76 | Project | 1 | 11-20-2012 05:43 AM |
I am unsure I assigned a task out to a resource. | jsteczak | Project | 3 | 10-05-2012 04:41 AM |