JulieS JulieS is offline How to show planned% complete and actual% complete on the (Project Overview) dashboard report? Windows 7 64bit How to show planned% complete and actual% complete on the (Project Overview) dashboard report? Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You can take a snapshot using the Snipping tool - but the graphic will not translate to Excel.
Reply With Quote
 

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
How to show planned% complete and actual% complete on the (Project Overview) dashboard report? MS Project 2013 - Overview report error Imagios Project 15 02-05-2016 09:21 AM
How to show planned% complete and actual% complete on the (Project Overview) dashboard report? Planned % Complete not showing on summaries Guloluseus Project 1 11-30-2015 05:11 PM
After open Project Overview Dashobard report, its blank anurag9179 Project 3 01-15-2015 06:57 AM
How to show planned% complete and actual% complete on the (Project Overview) dashboard report? Microsoft Project Managing Planned / Earned Value & Actual Costs shane_dav71 Project 1 10-06-2014 06:07 PM
How to show planned% complete and actual% complete on the (Project Overview) dashboard report? % Complete (Actual) vs % Complete (Should) Carlos Maximo Project 3 12-06-2011 12:01 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 05:17 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft