One central resource pool - six separate sharer plans
Resources are taken from the resource pool however within each project the charge rates vary (have updated via Cost rate table and formulae based on the jobs multiplier). How do I prevent the resource pool updating with the sharer plans different costs? |
#2
|
|||
|
|||
![]()
Make sure each of the 6 sharer files are set to "pool takes precedence" when you connect to the pool file. The rates should be in the resource pool - not the sharer files.
|
![]() |