I have a project in MS Project 2013 that has many over allocated tasks. I do not have enough resources to finish the project by the due date. I need to figure out how many people to hire. Can Project automatically choose from group of resources/people who has the available time tor the task?
|
#2
|
|||
|
|||
![]()
No. Project cannot and will not automatically assign resources in any manner. You can use the Assign resources dialog and filter for resources who are available for X hours during a selected task duration.
|
![]() |