Thread: [Solved] Leveling Resources Help!
View Single Post
 
Old 09-25-2015, 08:25 AM
JulieS JulieS is offline Windows 7 64bit Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

No. Project cannot and will not automatically assign resources in any manner. You can use the Assign resources dialog and filter for resources who are available for X hours during a selected task duration.
Reply With Quote